Activities

List of project activities with organisations that will implement each activity, expected results outputs and deliverables and the time period.

 NameOrg.OutputPeriod
1 Interface with EU authorities and coordination. INGV Communications and Internal Report Jan 2012
Dec 2013
2 Technical analysis of the communication problems related to the identification and designation of CIs in the interested area. INGV
CNIT
Technical Report Jan 2012
Sep 2012
3 Determination of the topology of high survival radio communication network. INGV
CNIT
Technical Report Jan 2012
Sep 2012
4 Characterization of the minimal amount of information necessary for the survival of the CIs communication. INGV
CNIT
Technical Report Oct 2012
Jan 2013
5 Operative supervision of the network architecture. INGV
CNIT
Technical Report Jan 2013
Apr 2013
6 Analysis of the existing architecture of HF communication based on internet protocol access with reference to the above considered infrastructures. CNIT Technical Report Jan 2012
Jun 2012
7 Analysis of existing HF connection system in terms of software and hardware for internet connection. CNIT Technical Report Jan 2012
Jun 2012
8 Definition of the High survival HF radio network technical requirements. CNIT Technical Report Jan 2012
Jun 2012
9 Radio network system design. CNIT Technical Report Jan 2012
Dec 2012
10 Criteria of early warning alert and procedures to activate the back up network. CNIT Technical Report Jan 2012
Dec 2012
11 Monthly prediction of the hourly HF set of frequencies over the n radio links given by the network, based on the available ionospheric model and methods. INGV
EO
Technical Report Jan 2013
Apr 2013
12 Daily forecasting of the hourly HF set of frequencies based on the Mediterranean ionospheric measurements. INGV
EO
Technical Report Jan 2013
Apr 2013
13 Ground wave propagation analysis when required. INGV Technical Report Aug 2013
Dec 2013
14 Frequency management system for HF communication link optimization.  INGV
EO
Technical Report Aug 2013
Dec 2013
15 Identification of the professional profile able to maintain and operate network. INGV
CNIT
NOA
EO
Technical Report Oct 2013
Dec 2013
16 Dissemination of deliverables within communities informing about initiatives organised in the context of the project. INGV
CNIT
NOA
EO
Technical Report Oct 2013
Dec 2013
17 Professional training activities trough courses, workshops and conferences. INGV
CNIT
NOA
EO
Technical Report Oct 2013
Dec 2013
18 Assessment of the potential impact and feasibility of the project for ECIs and CGAs and final recommendations for the EC. INGV
CNIT
NOA
EO
Technical Report Oct 2013
Dec 2013
19 Realization of a demonstrator constituted by 4- terminals HF network. INGV
CNIT
Realization of the demonstrator Jan 2012
Dec 2013
More in this category: « In pills Proposal »